Power delays have real consequences. They stall housing, increase costs, threaten jobs, and put Colorado developments at risk.
redT Homes is calling for greater accountability, transparency, and reliable timelines from Xcel Energy.
redT Sues Xcel Energy
The Denver Post reports that redT Homes filed suit against Xcel Energy on August 25, 2026 in Denver District Court, alleging years of repeated delays connecting electrical service to its Denver residential projects — delays the company says triggered loan defaults, foreclosure proceedings, and buyers walking away after losing financing.
“Xcel is a monopoly. There is no second choice.”
— Nathan Adams, CEO, redT Homes
redT Isn’t the Only One
The story found the same pattern playing out across Colorado:
- A Denver accessory-dwelling-unit developer waited five months for a power line relocation that Xcel crews finished in a matter of hours.
- A bottling plant planned near Denver International Airport was scrapped entirely after repeated attempts to get power to the site failed, taking hundreds of potential jobs to Colorado Springs Utilities instead.
- Public Utilities Commission staff have logged the same complaints from other large-load customers: long waits, inconsistent communication, and little clarity about where a project stands in Xcel’s queue.
Xcel has pointed to a surge in large-load service requests — 18 in 2024 compared with two or three a year previously — along with staffing shortages, as contributing factors.
Read the full story: Denver Post: Xcel faces backlash from Colorado developers over power-connection delays